Civil Engineers Guide

A guide for Civil Engineers
Menu
  • Home
  • About Us
  • Privacy Policy
  • Contact Us

Learn Civil Engineering Today!

Join Us Now For Free
Home
Civil Engineering
How To Determine Steel Bar Quantity for Matt Foundation, Columns, Slab-On-Grade And Suspended Slab

How To Determine Steel Bar Quantity for Matt Foundation, Columns, Slab-On-Grade And Suspended Slab

Noel Mades March 20, 2019

Preparing quantity for steel bars in every construction is a laborious work. It needs a skilled and experienced quantity surveyor, estimators or engineers to create one. Every section, sub-section, and parts of the plans with reinforcing bars should be included as missing one would be costly and ruinous in the long run.

Determining the reinforcing steel bars quantity for every section of the construction project is not the only thing that construction managers have to consider but also anticipating the actual needed on site. Some projects may need more than what is on the plan. Like for example, a column needs to be lengthened further due to embankments to attain the needed elevation and the project timeline is on its dead ends. Although this should be addressed by change orders, that is where skilled and efficient construction managers come in as they should be able to anticipate it first hand.

Mat Foundation

Considering a large amount on quantities for matt foundations, it is required to a lot ample amount of wastage for preparing steel bar quantity. By definition, mat or raft foundation transmit the load from the column, walls and the weight of the structure above it through the entire ground area. Being the stress distributor to the ground, it has to be designed by engineers to act as a slab and foundation. Thus, it is essentially a thickened slab but acts as the main foundation commonly ranging from 0.5 meters to 1.00 meter used in condominiums, buildings and treatment plants.

The following should help engineers on points to consider in determining the reinforcing bar quantity for matt foundation.


• Anticipate if it is required to use reinforcing bars for formworks and scaffolds for support and stability.

• Check the plans for the bottom and top bars’ spacing, length, and width. Consider the hooks and bends on each both sides as designed and add it to the total length.

• Inspect the plan for designed splicing lengths and add it to the total length. Splicing is the linking of two different reinforcing bars to attain the required total length.

• Examine the plan for other bars needed say, chair bar. Due to the lengthy height of mat foundation, designers use chair bars as concrete spacers to separate top bars and bottom bars.

Related: 10 Factors That Causes of Cracking Concrete

Below is a sample calculation for mat foundation rebar quantity.

t =1.00 m
W = 100 m
L = 100 m
S = 0.3 m

Commercial length per reinforcing bars = 12 l.m. , (to be deducted with splicing length @ 0.8m)

Top bars

Transverse quantity = W/s= 100/0,3=333.3,say 334 pcs100 l.m.
100 + t + t = 100 + 1 + 1 = 102 l.m., 334 pcs (Additional length for hooks)
334 X 102 = 34,068 total linear meter

(Total linear meter)/(commercial length-splicing)= 34,068/(12-0.8)=3,042 pcs-12meter length reinforcing bars

Longitudinal quantity = L/s= 100/0,3=333.3,say 334 pcs100 l.m.
100 + t + t = 100 + 1 + 1 = 102 l.m., 334 pcs (Additional length for hooks)
334 X 102 = 34,068 total linear meter

(Total linear meter)/(commercial length-splicing)= 34,068/(12-0.8)=3,042 pcs-12meter length reinforcing bars

Total Quantity for TOP BARS

Transverse QTY + Longitudinal QTY = 3,042 + 3,042 = 6,084 pcs – 12mL reinforcing bars

Calculating bottom bars is the same as the top bars. It is then the engineer’s discretion as to how much wastage factor will he add.

Columns

Columns are pillars used in buildings to transmit loads from upper ground to lower ground or to the foundation. Being the bridge from level to level structures, quantifying the reinforcing bars for column has to be prepared thoroughly.

Here is a guide on determining the quantity for reinforcing bars for column.

• Scrutinize the plan for reinforcing bars diameter, grade, and length per floor level. Do not forget to add the additional length from the foundation to the desired floor level lines should there be a need for embankments.

• Add the bend’s length per end to the initial level-to-level length. This is applicable for main bars and extra bars.

• For the ties, consider the bends, seismic hooks and total perimeter (minus the offsets) of the column. Most quantity surveyors and estimators count the ties per column as some column may be longer than the other column.

• Check the column should if there are additional bars required and add the required percentage for wastage.

Related: Introduction to The Field of Civil Engineering and Its Importance

Sample calculation:

W = 0.4 m
L = 1.0 m
H = 3.0 m
Main bar pcs. = 16
Total number of ties = 20 pcs.

Commercial length of reinforcing bars = 8.0 l.m.

Main bar

Length = H + hooks per ends = 3.0 m + 0.4 + 0.4 = 3.8 m (assumed length for hooks)
Total Length for main bar = L x no. of pieces = 3.8 x 16 = 60.8 l.m.
Total number of pieces = (Total Length)/(Commercial Length)= 60.8/8=7.6,say 8 pcs-8meter Length rebar

Reinforcing Ties

Length per ties is the perimeter, P = 2W + 2L = 2(0.4) + 2(1.0) = 2.8 m
Total length = Length x No. of ties = 2.8 x 20 = 56 linear meter
Total number of pieces = (Total length)/(Commercial length) 56/8=7 pieces-8 meter length rebars


Slab on Grade

Slab-on-grade is the floor that is earth exposed. Being exposed to moisture and direct seismic activity due to the ground, there should be no room for missed reinforcing bars not included in the total quantity. Quantity surveyors should be very keen on estimating reinforcing bars for slab on grade as missing even a single bar would be disastrous.

• The following will help engineers on determining the quantity of reinforcing bars in slab on grade.
Check the area of the slab on grade and scrutinize the plan carefully.

• Some area, especially near the stairs, may need dowels. Add the required dowels and its length as per designed plan.

• Add the hooks and splicing (as discussed above) to the total length. Take note that splicing lengths for matt foundation may differ to the splicing of slab on grade.

• Some slab on grade may be thickened near walls or door openings. Inspect should there be variations to seismic hooks and bends.

• Add the required percentage wastage to the total computed quantities.

Sample calculation.

Temperature bars

L = 10.0 m
W = 10.0 m
t = 0.6 m
s = 0.25 m

Commercial length of reinforcing bars = 12.0 l.m.

Transverse bars (same calculation for longitudinal bars because this is a square SOG)
No. of pieces = W/s= 10/0.25= 40 pieces-12 linear meter
Total number of pieces = Transverse + Longitudinal = 40 + 40 = 80 pcs – 12 linear meter reinforcing bars
Note: 12 linear meters commercial length is used instead of 10 to cater the seismic hooks per ends.

Related: How to Inspect a Footing Prior to Pouring Concrete

Read also: Structural Engineering And Its Importance In Designing A Building


Suspended Slab

Suspended slabs are technically slabs that are elevated. These may be in a form of canopy, terrace or the entire floor itself. Computing the required reinforcing bars may be tricky as there are two forms of slabs, one-way slab, and two-way slab. Further, there are areas that should be deducted like the stair openings or duct-work line openings. Thus, only experienced quantity surveyors should be the one doing these calculations.

The following guide should help you determine the required reinforcing bars for suspended slabs.

• Determine the tops bars spacing as per transverse and longitudinal bars.

• Add the hooks and splicing to the length as co mputed above.

• Any openings like stairs opening should be deducted to the calculations.

•Examine the plan if there are bends due to change in floor elevations. Suspended slabs that are associated with water are essentially lowered at least an inch from the rest of the entire floor like comfort rooms and terraces. Having being lowered, there may also be changes to the structural details of the slabs. These bends should be included in the calculations of the reinforcing bars.

• Add the needed dowels for masonry works like walls and concrete railings on the total quantity.

• Multiply the required percentage provision for the wastage factor.

Quantity calculation for suspended slab is technically the same with the slab-on-grade and mat foundation. Please see the calculations on top.

Quantifying and determining the reinforcing bars for any construction projects should be done only by competitive quantity surveyors and engineers. Missing one would mean missing the actual needed monetary needs required to finish the project on time. Business as it is, one needs to finish the project on time to get away with any liquidation damages. Further, if construction managers finish the project on time, it would mean savings which are good for the construction project. Thus, it is very essential to do it right thing the first time before any further damages happen.

Share
Tweet
Linkedin
Stumble
Pinterest
Email
Prev Article
Next Article

Related Articles

erectscaffolfing
Do you know scaffolding? Have you ever used it? When …

How To Erect Scaffolding: Step by Step Guide

Building a home is everyone’s dream. It is important that …

4 Common Problems to Look Out to When Building Your First House

Construction Manager plays an important role in building construction. They …

7 Major Works of a Construction Manager

projectengineer
Project engineers are one of the most relevant site personnel …

7 Major Works of a Project Engineer

About The Author

Noel Mades

Hi! My name is Noel Mades and I am the author of this blog. Welcome to my blog. I guess you are here because you are searching for information about civil engineering that I am writing on.

Leave a Reply

Cancel reply

This site uses Akismet to reduce spam. Learn how your comment data is processed .

Search

Get more stuff like this in your inbox

Subscribe to our mailing list and get interesting stuff and updates to your email inbox.

Thank you for subscribing.

Something went wrong.

we respect your privacy and take protecting it seriously

Categories

  • Popular
  • Recent
  • Comments

Civil Engineers Guide

A guide for Civil Engineers

About Us

Hi! Welcome to our site. This site is owned by Noel Mades. He designed civilengineersguidedotcom to serve his fellow Civil Engineers.

The site is all about Civil Engineering, Civil Engineers Jobs, and including Civil Engineering Design and Terminologies which also involves Geotechnical or Hydraulic Engineering.. Visit here

Archives

  • April 2019
  • March 2019
  • February 2019
  • January 2019
  • September 2018
  • May 2018
  • April 2018
  • March 2018
  • February 2018

Connect With Us

Copyright © 2023 Civil Engineers Guide
Theme by MyThemeShop.com

Ad Blocker Detected

Our website is made possible by displaying online advertisements to our visitors. Please consider supporting us by disabling your ad blocker.

Refresh